Manufacturing times (in working days) are subject to changes beyond our control. We have included this list as a guide on what to expect when all the ducks are lined up. We suggest contacting us first if you have a limited lead time as we do not wish to disappoint.
Lysaght products: Orders can take up to 48hrs to be entered into the Lysaght system. Most goods require manufacturing, and most regular sheeting and purlins are rolled within 7-10 working days after keying and before delivery or pick-up can commence. Production Schedules do vary from location to location and product to product. Some items have longer lead times of up to 4 weeks. If timing is a concern, please contact us first and we will get an estimated production time. Some products get manufactured interstate and shipped to local outlets.
Apex and Knee plates: are manufactured to order and currently have a minimum of 10 working days lead time plus shipping. The production schedule can vary outwards based on how busy the turret punch is. Lead times are currently up and are at least 10 working days. We suggest allowing 15 working days and an extra 3-5 days for the hot-dipped galvanised brackets like feet/footing brackets.
Footing Brackets: need to be hot-dipped in Gal and can take an additional 5 working days. Shed bracket orders with footing brackets tend to be 15 working days minimum.
Windows: ** Window lead times have moved out due to very high demand. expect 3-4 weeks **. The manufacture queue is usually from 10 to 14 working days before dispatch. This is longer for non-standard custom orders and at busy times of the year. The important message below is about window deliveries. (Custom size windows, Opaque, Toughened and Grey Tint Glass lead times are extended currently due to high demand, can be up to 12 weeks)
Larnec PA doors: production times are currently up, Standard 650/37/61 doors 10-15 days, Standard Sentry 200/47 15 days, other doors 20 days +, non-standard sizes, Double doors, customs, ultra skins and screened doors allow min 22 working days before dispatch.
Taurean PA doors: Pick up from various national depots usually approx 20-25 working days after order. Freighted – Doors are usually dispatched within 20-25 working days of the order. Delivery times are dependent on where in the order, manufacture cycle things fall and site location.
Vermin and ember seal products– usually despatched within 3-5 working days.
Shed Stairs: manufacture time is usually approx 10-20 working days dependent on the amount of hot-dip gal components.
Stable Panels: Currently 7-8 week lead time. Can be 4-5 Weeks, but currently 8 weeks.
XtraLocks: Usually dispatched in 2 working days via regular Australia Post or Aramex.
Orders received after 12:00 pm on any day may be deemed to have been received on the next working day due to manufacturers’ order confirmation time frame requirements.